5.12 Approval of Park Hill South Restroom Renovations (2022 Bond Projects)
|
Strategic Plan:
|
2023-2028 CSIP GOAL Build successful futures for Park Hill students of all backgrounds
|
Provide Name(s) of Attachments
|
Recommendation Letter
|
File Attachment:
|
|
Provide Background Details and Rationale:
|
These contractors, if approved, will provide work for Restroom Renovations identified during the design process for the 2022 No-Tax Increase Bond projects. Bids were received for the following packages.
*BP-042 Masonry
*BP-061 General Trades
*BP-081 Doors, Frames & Hardware
*BP-092 Metal Studs & Drywall
*BP-093 Ceramic Tiling
*BP-097 Resinous Flooring
*BP-099 Painting
*BP-210 Fire Protection
*BP-220 Plumbing
*BP-230 HVAC
*BP-260 Electrical
|
Provide Funding Source and Estimated Cost:
|
Funding will be provided from the 2022 No-Tax Increase Bond funds. The estimated cost of the total project is $1,739,000. The total for these packages is $1,292,384. District staff is recommending the bids from the following contractors to perform the work:
*BP-042 Masonry - Core Constructors - $202,773
*BP-061 General Trades - D.H. Pace - $314,835
*BP-081 Doors, Frames & Hardware - Omega Doors & Hardware - $5,510
*BP-092 Metal Studs & Drywall - Whitney Construction - $48,984
*BP-093 Ceramic Tiling - Midland Marble - $15,800
*BP-097 Resinous Flooring - Insco Industries - $81,045
*BP-099 Painting - MVP - $22,300
*BP-210 Fire Protection - Conley Sprinkler - $10,308
*BP-220 Plumbing - Genesis Plumbing - $499,979
*BP-230 HVAC - Edwards McDowell - $22,500
*BP-260 Electrical - Clayco Electric - $68,350
|
Legal References
:
|
N/A
|
Name of Persons(s) Submitting Agenda Item with Title
:
|
Jim Rich, Director of Operations Dr. Paul Kelly, Assistant Superintendent for Business & Technology
|
Presenter(s) if Presentation Anticipated
:
|
N/A
|
Recommendation:
|
It is recommended that the Park Hill Board of Education approve Park Hill South Restroom Renovations, as presented.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Jim Rich - Director of Operations
|
|
Signed By:
|
|
Dr. Paul Kelly - Assistant Superintendent - Business & Technology
|
|
Signed By:
|
|
Dr. Mike Kimbrel - Superintendent
|
|
|
|
|
|
|
|